The University of Texas at Austin is launching a multiyear effort to restore, revitalize and reimagine its historic Tower, an iconic, enduring symbol of the University. This marks the first meaningful investment in the Tower since its completion in 1937. This webpage serves as a resource for up-to-date information on restoration activities.
What's Happening Next
October 2024
The UFCU ATM at the west entry of the Main Building has been decommissioned and removed. Alternative ATMs are located outside the Flawn Academic Center or at the UFCU University Branch at 2244 Guadalupe Street. Aesthetic and safety improvements are in progress.
December 2024
Planning, Design and Construction will begin cordoning off the north parking lot.
Impacts to Building Occupants
Project Timeline:
Exterior restoration will begin in mid-December 2024, beginning with blocking the parking lot north of the Main Building. Scaffolding erection will begin in early January on the Main Building. Restoration work on the Tower will begin during the summer of 2025. Restoration of both the Main Building and the Tower is expected to be complete during the summer of 2027.
Entrance and Exit Impacts During Construction:
The north parking lot will remain closed from December 2024 to the summer of 2027. Pedestrian exits from the building will remain unaffected, but the entrance on the north side of the building will be temporarily closed. Handicap-accessible entrances and exits will remain at the east and west entries. There will be construction fencing and protective covers for pedestrian paths where necessary to protect the safety of the public.
Restoration Activity Considerations for Building Occupants
Throughout multiple stages of restoration, there may be noise impacts, such as sandblasting during abatement. The sound will carry through open areas and into closed offices. Construction crews will move from window to window. Workspaces may be affected by the sound of activity at adjacent spaces’ windows. Staff members in spaces with windows on multiple sides of the building may be affected several times throughout the project.
The video clips below give a preview of the interior noise level experienced due to nearby exterior construction activity.
Abatement containment and noise within room
Abatement noise within suite
Abatement noise with door closed
Abatement noise from floor below work
The restoration project is not responsible for identifying alternative work locations, but if on-campus workspace accommodations are considered necessary and cannot be resolved by departments, those accommodations must be requested of MainRestoration@austin.utexas.edu at least three weeks in advance.
Abatement Activity
Abatement is a set of procedures happening ahead of construction to control or eliminate preexisting hazardous materials, such as asbestos or lead that were used in historical construction. For this project, zones around window areas will be sealed off with double layers of plastic to keep any loose material from leaving the area.
Each suite and office area in the Main Building and Tower is unique. To prepare for construction, project managers will walk through each space in advance to create a plan for shifting or moving office furniture currently within 12 feet of a window to enable adequate clearance for abatement and construction activities. The project team recommends that occupants pack and move personal items out of their space before the project’s movers begin their work. For special accommodations, email MainRestoration@austin.utexas.edu.
The project team will provide guidance on when furniture and personal effects can return.
Contact the project team with questions and comments at MainRestoration@austin.utexas.edu.
Frequently Asked Questions
What will the project entail?
The initial work will be a comprehensive restoration of the Tower’s exterior, including the stone, windows, lighting, clockface and historical gilding on the facade of the building. Matching the building’s original appearance, the University will repaint metal and wooden surfaces in their original colors, reapply gilding to the Tower clock and cast-iron spandrels, and reconstruct the east and west entrances. The work also includes updating the exterior lighting to an LED-based system, replacing select roofs, and refurbishing windows to improve their appearance, operability and energy efficiency.
Scaffolding and restoration work will be done in sequence on every facade of the Main Building and Tower, starting with the northern perimeter of the Main Building. The work will take place concurrently on multiple sides until the entire building is restored.
Will scaffolding be up during the entire restoration? How can people take photos in front of the Tower during restoration?
To reach project milestones, the Main Building will sequentially have scaffolding on various facades through the summer of 2027.
The project timeline calls for the scaffolding to begin rising on the north facade of the Main Building in January. However, the construction will not advance to cover the Tower and south facade of the Main Building until after the University’s 2025 commencement celebration. The schedule may evolve throughout the course of the project due to weather or unforeseen conditions.
Students who are expecting to graduate during 2026 and 2027 should make plans to capture those special Tower photos throughout the year, prior to the scaffolding and scrim covering the building.
What is the difference between the Tower and Main?
For the purposes of this project, the Main Building includes levels 9 and below (the areas in yellow in the diagram). The Tower comprises levels 10 and above (depicted in orange in the diagram).
Will the Tower be able to be lit during restoration?
Traditional lighting will be affected. However, the restoration project team will provide lighting throughout construction, ensuring the celebration of athletic and academic achievements, calendar milestones and other events.
How will my workspace be protected during construction activity?
The abatement and construction containment will protect office spaces from being affected by dust from construction activity. When windows are temporarily removed for off-site refurbishment, the window openings will be temporarily sealed and boarded up.
When will my office be impacted?
When more information is provided for the project schedule, it will be announced here.