What's Happening Next
Phase One
This phase impacts the areas surrounding FC8 and the north and west side of FC3. Work is expected to last 12 days.
The work includes:
- Shed relocation and gravel surfacing
- Concrete parking stops relocation
- Striping
Phase Two
This phase impacts the areas surrounding FC5 and the west side of FC9. Work is expected to last 8 days.
The work includes:
- Demolition of concrete curb
- Form and rebar installation
- Adding concrete
- Striping
Phase Three
This phase impacts the north side of FC2 and the west side of FC4. Work is expected to last 12 days.
The work includes:
- Demolition of concrete curb
- Form and rebar installation
- Adding concrete
- Striping
Phase Four
This phase impacts the south side of FC3 and the north side of FC4. Work is expected to last 17 days.
The work includes:
- Demolition of concrete curb
- Form and rebar installation
- Adding concrete
- Striping