What's Happening Next
We are now heading into the final phases of this project which include power washing and striping. Power washing will begin on Wednesday, May 7 at 7 a.m. and will be complete by 3 p.m. Striping will occur on Friday, May 9 from 2 a.m. to 3 p.m. While work is occurring, please anticipate not being able to park in your designated area. Managers of the affected shops will be reminded by the project manager that fleet vehicles will need to be temporarily relocated.

Phase One
This phase impacts the areas surrounding FC8 and the north and west side of FC3. Work is expected to last 12 days.
The work includes:
- Shed relocation and gravel surfacing
- Concrete parking stops relocation
- Striping
Phase Two
This phase impacts the areas surrounding FC5 and the west side of FC9. Work is expected to last 8 days.
The work includes:
- Demolition of concrete curb
- Form and rebar installation
- Adding concrete
- Striping
Phase Three
This phase impacts the north side of FC2 and the west side of FC4. Work is expected to last 12 days.
The work includes:
- Demolition of concrete curb
- Form and rebar installation
- Adding concrete
- Striping
Phase Four
This phase impacts the south side of FC3 and the north side of FC4. Work is expected to last 17 days.
The work includes:
- Demolition of concrete curb
- Form and rebar installation
- Adding concrete
- Striping